GME – chillar project

Project Details

The Chiller Project was executed in the Industrial Zone, 6th of October, spanning from 2008 to 2023.

Owner and Consultant

The project was owned by GME, with MEG serving as the consultant.

Scope of Work

The scope encompassed the supply and installation of a new chiller unit manufactured by Trane Company, along with a complete piping network. The project also involved the supply and installation of four axial pumps integrated with a full piping system. Additionally, it included the dismantling of old pumps and existing piping, as well as the fabrication and erection of all related steel structures to ensure optimal performance and system efficiency.